Church Street Site A Demolition – Keltbray Built Environment Ltd Contract Variation and Extension
July 14, 2025 Cabinet Member for Regeneration and Renters (Cabinet member) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...they approved a £2,940,141 variation to the contract with Keltbray Built Environment Ltd for additional demolition works at Church Street Site A, increasing the contract sum to £6,310,634, and extended the contract programme by six months to November 2025.
Full council record
Purpose
The Cabinet Member will consider the variation
to the contract with Keltbray Built
Environment Ltd to progress the demolition of Church Street Site
A.
Decision
Summary of Decision: The Cabinet Member
for Regeneration and Renters has noted the additional variation sum
of £2,940,141 in respect of additional demolition works which
has already been incurred to date to Church Street Site A, Phases 2
and 3, increasing demolition works contract sum to
£6,310,634, and approved an extension of time to the contract
programme for a period of six (6) months from May 2025 to November
2025.
Reasons for Decision: A number of
discoveries have been made as part of the demolition which includes
the discovery of additional asbestos, discovery of underground
unknowns, extension to scope of works and additional costs in
relation to nesting birds. These have caused delays to the
demolition and incurred additional costs.