291 Harrow Road - Multi-Discipline Consultant Team (MDCT) Appointment

December 6, 2023 Cabinet Member for Climate Action, Regeneration and Renters (Cabinet member) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to progress the redevelopment of 291 Harrow Road, the Council will enter into professional services contracts totaling £4.84m with several firms for design development, delegate authority for additional costs, and approve further expenditure to advance the scheme to Outline Business Case Part 2.

Full council record

Decision

Summary of Decision

The Cabinet Member for Climate Action, Regeneration and Renters has approved:

  1. The Council to enter into Professional Services contracts with a value greater than £300k totalling £4.84m to carry out design development., including the appointment of the following:
  2. 1.     Carter Gregson Gray as Architect (contract value £1.74m)
  3. 2.     Arcadis LLP as Project Manager (contract value £1.14m)
  4. 3.     Ward Williams Associates as Cost Consultant (contract value £606k)
  5. 4.     CR8 Structures as Structural and Civil Engineer (contract value £456k)
  6. 5.     Hoare Lea as Mechanical, Electrical & Plumbing Engineer (contract value £566k)
  7. 6.     Farrer Huxley as Landscape Architect (contract value £329k)
  8. The delegation of authority to the Executive Director of Regeneration, Economy and Planning (REP) to approve other Professional Services and associated costs totalling £3.44m. Where the Constitution does not allow for the Cabinet Member to delegate authority (namely for the award of Consultancy contracts with a value greater than £300,000).
  9. Additional expenditure of £796k to progress the scheme to Outline Business Case Part 2 (total expenditure £2.148m).
  10. The noting of the balance of expenditure under these contracts and other Professional Services and associated costs (totalling £6.128m) will come forward for approval once an OBC is concluded in 2025. A breakdown of the costs can be found in Appendix A (Financial Implications).
  11. The noting that any potential additional development options to be progressed beyond the feasibility stage options analysis (RIBA Stage 1) would be the subject of a separate decision which is required to return to CRG in consultation with the Cabinet Member for additional budget and expenditure approvals.

Reasons for Decision

The reason for the recommendation is to secure fees and appoint the design team to enable design development to be progressed and produce the Outline Business Case in Spring 2025.

In order to support design development, the following core MDCT consultants are required to provide technical and specialist support:

·       Architect

·       Project Manager

·       Cost Consultant

·       Structural & Civil Engineer

·       Mechanical, Electrical and Plumbing (MEP) Engineer

·       Planning Consultant

·       Landscape Architect

Supporting Documents

Statement of Decision 291.pdf
CMR - 291 Harrow Road MDCT Appointment.pdf

Details

OutcomeRecommendations Approved
Decision date6 Dec 2023
Effective from14 Dec 2023
Subject to call-inYes