470 Harrow Road Contract Variation

October 23, 2023 Cabinet Member for Planning and Economic Development (Cabinet member) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to settle Rooff Limited's final account for the 470 Harrow Road refurbishment, a contract variation of £280,267.49 was approved, bringing the total contract value to £1,621,689.51.

Full council record

Decision

Summary of Decision

The Cabinet Member for Planning and Economic Development has approved the contract variation of £280,267.49 required for the Council to settle Rooff Limited’s final account submitted for payment.

Reasons for Decision

The works have now been completed and the contractor’s Final Account has been finalised with the contractor. Approval is required for the contractor’s Final Account sum so it can be paid by the Council.

A Cabinet Member Decision is required due to the total contract value.  

Supporting Documents

SIGNED CMR 470 Harrow Road Contract Variation.pdf

Details

OutcomeRecommendations Approved
Decision date23 Oct 2023
Effective from31 Oct 2023
Subject to call-inYes