Lisson Arches Development

October 20, 2023 Cabinet Member for Finance and Council Reform (Cabinet member) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to approve an additional £3,203,958 expenditure for the Lisson Arches Development, increasing the final construction contract amount to £27,801,133, funded from Affordable Housing Fund receipts.

Full council record

Decision

Summary of Decision

The Cabinet Member for Finance and Council Reform has, in consultation with the Cabinet Member for Climate Action Regeneration and Renters and the Cabinet Member for Housing Services:

·         Approved the additional £3,203,958 variance spend to the original signed construction contract so the final account to be agreed between the Council and ULS for the works delivered shall be £27,801,133.

·         Noted the increase in budget of £3.3m will be funded from the Affordable Housing Fund receipts.

Reasons for Decision

The project is approaching the practical completion stage and under the construction contract, a final account agreement is required between the WCC and ULS.

The original Cabinet Member decision was published on 8th March 2021. Throughout the course of the project, a number of changes have been instructed under the contract. There have also been loss & expense claims submitted by the contractor. WCC and ULS have now come to a commercial agreement with regards to the final account. The proposed final account now stands at £27,801,133 this represents a variance of £3,203,958 against the original contract sum approved and awarded by the Council.

Supporting Documents

SIGNED Cabinet Member Report - Lisson Arches Final Account.pdf

Details

OutcomeRecommendations Approved
Decision date20 Oct 2023
Effective from28 Oct 2023
Subject to call-inYes