Ashbridge, Ashmill & Cosway sites - settlement of the main construction contract final account with Geoffrey Osborne Limited

September 13, 2023 Cabinet Member for Climate Action, Regeneration and Renters, Cabinet Member for Finance and Council Reform (Cabinet member) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Cabinet Member for Climate Action, Regeneration and Renters, Cabinet Member for Finance and Council Reform approved the additional £7,760,002 variance sum to the construction contract with Geoffrey Osborne Limited, and approved additional spend of £8.8m against the previously approved spend to complete the scheme on 13/09/2023. They noted an increase in budget requirement of £4.347m above existing provision, to be funded from the Affordable Housing Fund.

Full council record

Purpose

Settlement of main construction contract account

Decision

Summary of Decision

The Cabinet Member for Finance and Council Reform and the Cabinet Member for Climate Action Regeneration and Renters in consultation with the Cabinet Member for Housing Services have:

·       Approved the additional £7,760,002 variance sum to the signed construction contract between the Council and Geoffrey Osborne Limited. The interim final account for the works delivered and agreed with the contractor amount to £51,250,000 (excluding VAT).

·       Approved the additional spend of £8.8m against the previously approved spend set out in the FBC to complete the scheme.

·       Noted the increase in budget requirement of £4.347m above existing provision which will be funded from the Affordable Housing Fund.

Reasons for Decision

The project is approaching the practical completion stage and under the construction contract, a final account statement is required to be agreed and signed between the Council and Osborne.

Supporting Documents

SIGNED Cabinet Member Report - Ashbridge Ashmill Cosway Final Account.pdf

Details

OutcomeRecommendations Approved
Decision date13 Sep 2023
Effective from21 Sep 2023
Subject to call-inYes