Ebury Bridge Estate Renewal - Supplemental Agreement to the Building Contract with Bouygues (UK) Ltd. Phase 1
July 20, 2023 Cabinet Member for Climate Action, Regeneration and Renters, Cabinet Member for Finance and Council Reform (Cabinet member) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve a £3.5 million increase to the contract sum and associated budget for Phase 1 of the Ebury Bridge Estate Renewal project with Bouygues (UK) Ltd. via a Deed of Variation.
Full council record
Decision
Summary of Decision
The Cabinet Member for Climate Action, Regeneration and Renters and the Cabinet Member for Finance and Council Reform have approved the variation to the contract made by way of Deed of variation including increasing the contract sum by £3.5m and approved the associated budget by £3.5m.
Reasons for Decision
Entering into the Deed of Variation is required to continue the delivery of Phase 1 of the Ebury Bridge Estate Regeneration in accordance with WCC’s policies and commitments to the renewal of the site.
The DoV closes out a significant amount of commercial items and reflects a fair and reasonable cost to the Council with future risk of both delay and additional cost transferred to the contractor.
Details
| Outcome | Recommendations Approved |
| Decision date | 20 Jul 2023 |
| Effective from | 28 Jul 2023 |
| Subject to call-in | Yes |