Ebury Bridge Estate Renewal - Electrical Substation Lease

July 11, 2023 Cabinet Member for Climate Action, Regeneration and Renters, Cabinet Member for Finance and Council Reform (Cabinet member) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Cabinet Member for Climate Action, Regeneration and Renters, Cabinet Member for Finance and Council Reform approved the lease of an electricity substation chamber and other property documents on 11/07/2023. The Executive Director of Growth Planning and Housing was delegated authority to approve and enter into these agreements.

Full council record

Decision

Summary of Decision

The Cabinet Member for Climate Action Regeneration & Renters and the Cabinet Member for Finance & Council Reform have:

·       Delegated to the Executive Director of Growth Planning and Housing authority to approve and enter into a lease of an electricity substation chamber at Phase 1 of the Ebury Bridge Estate regeneration.

·       Delegated to the Executive Director of Growth Planning and Housing authority to approve and enter into other agreements and property documents including but not limited to leases, warranties, substation leases, wayleaves, licences, deeds of easement, asset protection agreements, section 104 agreements, section 185 agreements and any other statutory agreements and utilities agreements in connection with ancillary works required to facilitate the construction works at Phase 1 of the Ebury Bridge Estate regeneration.

Reasons for Decision

The substation lease and all other statutory and utility leases/ easements/ wayleaves/leases/licences/deeds and agreements are deemed necessary contractual documents in order to complete all connections and disconnections to Phase 1 of the project to meet the critical path programme with the main contractor to complete the construction handover for occupation by Westminster City Council.

The power to grant leases of over 25 years are delegated to the relevant Cabinet Member.

Supporting Documents

Appendix 1 - Eclipse Substation Lease - Engrossment140644875.1.pdf
SIGNED CMR Ebury Phase 1 Substation Lease.pdf
Appendix 2 - EQIA July 2020.pdf

Details

OutcomeRecommendations Approved
Decision date11 Jul 2023