Oxford Street Programme – Oxford Street Scheme Stage 3

July 15, 2024 Cabinet (Cabinet collective) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

... to proceed with Stage 3 design of the Oxford Street Scheme, allocating £3.845m for this purpose, while acknowledging that the remaining funding from third parties is not yet formally secured.

Full council record

Purpose

To approvethat the
Oxford Street Scheme proceed
to Stage 3, detail design, as
part of the Oxford Street Programme.

Decision

Cabinet approved the
option to proceed to Stage 3
design on the basis set
out in the report in the knowledge that the remaining funding is
yet to be formally confirmed.  
 
Cabinet also
approved spend of £3.845m to progress the Stage
3 design.
 
Reasons for
Decision: The Stage 2 design for Oxford
Street is
complete and the finalisation of design is required in advance of
pre-mobilisation and construction. A decision is required on how to
progress the Oxford Street project. 
 
Implementation Date:
5pm 22/7/24

Supporting Documents

Oxford Street Programme Oxford Street Project Stage 3 Design - Cabinet Report.pdf

Details

OutcomeRecommendations Approved
Decision date15 Jul 2024
Subject to call-inYes