Ebury Phase 1 - QS Contract Variation
October 18, 2024 Executive Director of Regeneration, Economy and Planning (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve an increase of £144,852 (9.94%) to the existing contract with Gardiner & Theobald LLP for Quantity Surveyor services on the Ebury Phase 1 project, bringing the new total contract value to £1,602,352.
Full council record
Decision
The increase in the cost of the Quantity
Surveyor (QS) additional services is 9.94% increase on the agreed
original contract sum.
The additional costs have been based upon the
tendered rates contained within the contract sum and equality
objectives.
The Executive Director of Regeneration,
Economy and Planning has approved the additional expenditure
regarding the Council’s professional appointment contracts as
set out below in respect of Gardiner & Theobald (G&T) LLP
for Ebury Phase 1 for the Quantity Surveyor (QS) services:
·
Original Contract Value: £1,457,500
·
Variation Sum Increase: £144,852
(9.94%)
·
New Total Contract Value: £1,602,352
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 18 Oct 2024 |