Summary

...to approve an increase of £175,474 (9.63%) to the contract with Gardiner & Theobald LLP for Project Management and Employers’ Agent services for Ebury Phase 1, bringing the new total contract value to £1,997,097.

Full council record

Decision

The increase in the cost of the Project
Manager /Employers Agent (PM/EA) for additional services is 9.63%
increase on the agreed original contract sum.
 
The additional costs have been based upon the
tendered rates contained within the contract sum and equality
objectives. 
 
The Executive Director of Regeneration,
Economy and Planning has approved the additional expenditure
regarding the Council’s professional appointment contract as
set out below in respect of Gardiner & Theobald (G&T) LLP
for Ebury Phase 1 for the Project Management (PM) and
Employers’ Agent (EA) services.

·      
Original Contract Value: £1,821,623 

·      
Variation Sum Increase: £175,474
(9.63%)  

·      
New Total Contract Value: £1,997,097 
 