Subscribe to updates

You'll receive weekly summaries about Newham Council every week.

If you have any requests or comments please let us know at community@opencouncil.network. We can also provide custom updates on particular topics across councils.

Officer Key Decision - Thursday 4th January 2024

January 4, 2024 Officer Key Decision View on council website

Chat with this meeting

Subscribe to our professional plan to ask questions about this meeting.

“What key decisions did the officer make?”

Subscribe to chat
AI Generated

Summary

Open Council Network is an independent organisation. We report on Newham and are not the council. About us

We have not been able to find a video broadcast of this meeting.

Delegated decisions linked to this meeting

Decision summaries below are AI-generated from the council’s published record. Check the council source or the full decision page before relying on them.

  • Refurbishment Works, Medium Rise Blocks
    Decision approved (subject to call-in)

    Newham Council's Chief Executive, Abi Gbago, approved the award of a contract for refurbishment works at Greenhill Grove and Romford Road on 04/01/2024. The decision approved the award of the contract to Thomas Sinden Ltd for £992,829.58. The works include asbestos removal, repairs to roofs, brickwork, and cladding, as well as internal and external decorations.

    Council website ↗

Attendees

No attendees have been recorded for this meeting.

Topics

No topics have been identified for this meeting yet.

Meeting Documents

No documents have been uploaded for this meeting.