Subscribe to updates

You'll receive weekly summaries about Barking and Dagenham Council every week.

If you have any requests or comments please let us know at community@opencouncil.network. We can also provide custom updates on particular topics across councils.

Chat with this meeting

Subscribe to our professional plan to ask questions about this meeting.

“What risks will the committee audit?”

Subscribe to chat
AI Generated

Summary

Open Council Network is an independent organisation. We report on Barking and Dagenham and are not the council. About us

The Audit and Risk Committee of Barking and Dagenham Council met on Wednesday 1 July 2026 to discuss findings from the Local Government and Social Care Ombudsman, review external auditor plans, and consider internal audit reports. Key decisions included noting the Ombudsman's findings on a housing-related matter and approving the external auditor's plans for the 2025/26 financial year.

Ombudsman's Findings on Housing Matter

The committee received a report detailing the findings of the Local Government and Social Care Ombudsman (LGO) into a housing-related matter concerning Mr X. The LGO found fault causing injustice due to the Council's handling of Mr X's housing application and an Occupational Therapy (OT) assessment. Specifically, the Council failed to properly explain its decisions regarding Mr X's priority banding, inform him of his right to a review, and delayed reconsidering its decision. Furthermore, the Council was at fault for not conducting homelessness inquiries when informed Mr X's property was unsuitable and for delaying an OT assessment.

Councillor Maureen Worby, Cabinet Member for Housing, Adult Social Care and Health, and John Knight, Director of Housing, presented the report. The Council accepted the LGO's findings in full, paid £1,200 in compensation to Mr X, and has implemented or is in the process of completing the recommended actions. These include issuing an apology, reviewing housing options, and developing action plans to reduce the backlog of OT assessments and ensure homeless applications are taken appropriately. The Council acknowledged that while the family did not wish to be placed in temporary accommodation, the findings highlighted a failure to follow homelessness legislation. An action plan is to be produced by September 2026 to address these issues.

External Auditor's Audit Plans for 2025/26

Representatives from Grant Thornton, including Ellen Millington (Senior Audit Manager), Zargham Malik, and Terence Bershu, presented the external auditor's audit plans for the Council and the London Borough of Barking and Dagenham Pension Fund for the 2025/26 financial year.

A significant challenge highlighted was the ongoing impact of the backstop arrangements, which have led to disclaimed audit opinions for several years. Grant Thornton aims to complete all local authority audits within a shorter timeframe, with an objective to issue audit opinions by 30 November 2026. This is a crucial step towards developing a sustainable process to move away from disclaimed audit opinions.

Key risks identified for the Council's audit include management override of controls, valuation of property assets (including council dwellings and investment properties), pension fund net liability, and the implementation of IFRS 16. For the Pension Fund, significant risks include management override of controls, valuation of level three investments, and the disclosure of actuarial valuation under IAS 26.

The auditors noted that while they had identified five significant weaknesses related to the Council's financial sustainability and improving economy, efficiency, and effectiveness, these arose from prior-year recommendations. Further work will be undertaken to assess progress. The proposed audit fees were also presented, with a scale fee of £501,208 for the Council and £96,882 for the Pension Fund.

Regaining Assurance Strategy

Grant Thornton also presented a proposed strategy for regaining assurance over the Council's audits, in response to a request from the Ministry of Housing, Communities and Local Government (MHCLG). This strategy outlines a three-year plan to rebuild assurance, focusing on achieving a qualified opinion by 2027/28. The Authority was provisionally assessed as Category D under the MHCLG capacity assessment framework, indicating practical constraints to achieving a fully ISA-compliant approach by 2027/28. Technical challenges, including complex group structures and lease arrangements, alongside capacity issues within the Authority, were identified as key factors. The strategy prioritises gaining assurance over in-year transactions and closing balances for 2025/26, with a target sign-off by 30 November 2026.

2025/26 Accounts and Audit Update

Nurul Alom, Head of Corporate Finance, provided an update on the preparation of the 2025/26 Statement of Accounts. He noted that the report was drafted prior to the publication of the draft statements of accounts, which occurred the previous day. Officers were working on uploading working papers to meet the agreed timeline with Grant Thornton. The report highlighted the accelerated audit timetable, with a target completion by 30 November 2026, ahead of the statutory backstop date of 31 January 2027. Improvements implemented include earlier planning, strengthened engagement with subsidiary auditors, enhanced training, and the use of additional specialist and interim resources. The report also detailed the audit timelines and key focus areas, aligning with the significant risks identified by Grant Thornton.

Draft Annual Governance Statement 2025/26

Nurul Alom also presented the draft Annual Governance Statement (AGS) for 2025/26. The statement assesses the Council's governance, risk management, and internal control arrangements, concluding that they are generally in place and operating effectively, with a positive direction of travel. However, it also identified key governance challenges, including staffing, the Statement of Accounts process, value for money assessment, financial resilience, subsidiary company governance, the lack of a standalone Local Code of Corporate Governance, and building safety and regulatory compliance. Actions are in place to address these issues and are monitored through the Council's governance framework. The AGS will be updated following external audit work before final approval.

Internal Audit Annual Report 2025/26

Vanessa Bateman, Head of Assurance, presented the Internal Audit Annual Report for 2025/26. The Head of Internal Audit provided an overall opinion of generally satisfactory with some improvements required, indicating that the Council's framework of governance, risk management, and internal control is broadly effective, with some areas needing further strengthening. The report detailed the work completed, noting that 91% of the audit plan was delivered. Three audits resulted in limited assurance opinions: Section 17 compliance, governance of council and companies, and loans and investment arrangements. These highlighted areas require improvement in governance, oversight, and strategic requirements, with management action plans in place. Positively, no critical findings were raised.

Work Programme 2026/27

The committee reviewed its work programme for 2026/27, noting that it is a flexible document subject to change. It was agreed that the programme would include a review of group accounts and invitations for client representatives from subsidiary companies to attend future meetings. Members also discussed the potential for better dovetailing with the scrutiny committee's work.

The meeting concluded with the Chair declaring it closed at 9:01 pm.

Attendees

Profile image for Cllr Dorothy Akwaboah
Cllr Dorothy Akwaboah Chair of Audit & Risk Committee and Labour Group Treasurer Labour Party Alibon
Profile image for Cllr Phil Waker
Cllr Phil Waker Labour Party Village
Profile image for Cllr Maureen Worby
Cllr Maureen Worby Cabinet Member for Housing, Adult Social Care & Health Labour Party Eastbury
Profile image for Cllr Josie Channer
Cllr Josie Channer Deputy Chair of Audit & Risk Committee Labour Party Barking Riverside
Profile image for Cllr Mashkura Binta Mazid
Cllr Mashkura Binta Mazid Green Party Longbridge
Profile image for Cllr Shamsul Azam
Cllr Shamsul Azam Labour Party Mayesbrook
Profile image for Cllr Mohammed Khan
Cllr Mohammed Khan Deputy Chair of Full Council Labour Party Eastbury
Profile image for Cllr Caleb van Ryneveld
Cllr Caleb van Ryneveld Reform UK Goresbrook
Profile image for Cllr Mukhtar Yusuf
Cllr Mukhtar Yusuf Deputy Chair of Overview & Scrutiny Committee Labour Party Whalebone
Profile image for Cllr Rocky Gill
Cllr Rocky Gill Cabinet Member for Finance & Corporate Services Labour Party Longbridge

Topics

Croydon Regaining Assurance Strategy Southwark Council Climate Action Plan Tower Hamlets Council Housing Strategy Brent Council Transport Policy City of London Council Budget 2024 Grant Thornton Affordable Rent Cycling Infrastructure Air Quality digital transformation and inclusion Hate Crime Underreporting School Place Shortage Traffic and Parking Issues Homelessness Victoria Park Redevelopment Tower Hamlets Digital Council Initiative Southwark School Expansion Project Brent Council Levelling Up Fund Tower Hamlets Chief Planning Officer Southwark Chief Executive Ward Councillor for Bethnal Green North John Smith Councillor Jane Doe Mayor Johnson Tesco (Bethnal Green) Taylor Wimpey Capita Local Waste Management Ltd Dino's Italian Restaurant Age UK Local Community Trust Food Bank Network Barking and Dagenham Local Government & Social Care Ombudsman Housing-related matter Occupational Therapy (OT) assessment homelessness enquiries Cabinet Member for Housing, Adult Social Care and Health Director of Housing Strategy and Delivery homelessness legislation Barking and Dagenham's Pension Fund Disclaimed audit opinions IFRS 16 leases IAS26 Business Viability economy, efficiency, and effectiveness Ministry for Housing Communities and Local Government (MHCLG) ISA-compliant approach Group structure lease arrangements in-year transactions closing balances Director of Finance - Corporate Annual statement of accounts Annual Governance Statement (AGS) Financial and risk management matters Value for Money (VFM) review Financial Resilience - Inability to deliver a balanced budget subsidiary company governance Local Code of Corporate Governance Building safety and regulatory compliance Head of Assurance Internal control, governance, and risk management Scrutiny Group accounts Overview and Scrutiny Commission working papers subsidiary auditors internal control arrangements Section 17 compliance governance of council and companies loans and investment arrangements strategic requirements subsidiary companies

Meeting Documents

Agenda

Agenda frontsheet Wednesday 01-Jul-2026 19.00 Audit and Risk Committee.pdf

Reports Pack

Public reports pack Wednesday 01-Jul-2026 19.00 Audit and Risk Committee.pdf

Additional Documents

Vision Priorities Aug25.pdf
Minutes 25032026 Audit and Risk Committee.pdf
GT Audit Plan 25-26 App 1 Council.pdf
GT Audit Plan 25-26 App 2 Pension Fund.pdf
GT - Regaining Assurance Strategy June 2026_FINAL.pdf
APPENDIX 1.pdf
LGO covering report final.pdf
Appendix 1 - 2025-26 AGS.pdf
AR Work Programme 2026-27.pdf
2025-26 Accounts and Audit Report.pdf
Internal Audit Annual Report 2025-26.pdf
Internal Audit - App 1.pdf
Internal Audit - App 2.pdf
2025-26 AGS Report updated final.pdf
Printed minutes Wednesday 01-Jul-2026 19.00 Audit and Risk Committee.pdf