Officer Key Decision - Tuesday 28th July 2026 11.21 a.m.

July 28, 2026 Officer Key Decision View on council website

Chat with this meeting

Subscribe to our professional plan to ask questions about this meeting.

“What's the tender evaluation weighting for Roman Road School?”

Subscribe to chat
AI Generated

Summary

Open Council Network is an independent organisation. We report on Newham and are not the council. About us

The Officer Key Decision meeting scheduled for Tuesday 28 July 2026 was set to consider a report regarding decarbonisation works at Roman Road Primary School. The decision-making authority for this matter was delegated to a specific officer, with details of the final decision to be made available separately.

Roman Road School - Phase 1 Decarbonisation Works - Pre-procurement Approval

The primary item scheduled for discussion was the pre-procurement approval for Phase 1 decarbonisation works at Roman Road Primary School. The report indicated that the Corporate Director of Children's and Young People's Services, Laura Eden, was the decision-maker for this matter. The proposed works involve upgrading the school's heating and ventilation system, with an estimated budget of £0.957m.

The report outlined that Roman Road Primary School, built in the 1970s and subsequently expanded, currently has a gas heating system nearing the end of its operational life. To align with Newham's Just Transition Plan1, a decarbonisation survey was conducted to identify measures for reducing the school's reliance on fossil fuels. The planned upgrades are intended to be part-funded by the Department for Education's School Condition Programme (£0.605m) and the Salix Phase 4 Public Sector Decarbonisation Scheme grant (£0.352m).

The recommendation was to approve a procurement process to source a contractor with proven experience in delivering similar works within schools. The procurement would be conducted via the Oracle Fusion Request for Quotes (RFQ) Portal, inviting six contractors to tender. The evaluation criteria were proposed to be 60% price, 30% quality, and 10% social value. Following the tender evaluation, a further report would be submitted to seek permission to enter into a contract with the winning bidder.

The report highlighted that the project aligns with the council's Corporate Plan 2022–2026, aiming to invest in children and young people, and the Newham Just Transition Plan 2023, which seeks to reduce carbon emissions and ensure schools are healthy, comfortable, and efficient. The alternative option of do nothing was rejected due to the heating system's age and the need to maintain ambient temperatures for children's learning. Another rejected alternative was a different procurement route or cost and quality split, as the proposed method was recommended by the Strategic Procurement Team for achieving competitive bids and best value.

Financially, the estimated contractual cost is £0.957m, to be financed by the aforementioned grants. The Public Sector Decarbonisation budget for the school will be added to the capital programme following cabinet approval. Legally, the Council has the power to procure such works under Section 111 of the Local Government Act 1972 and the general power of competence under Section 1 of the Localism Act 2011. The procurement value falls below the threshold for the full Procurement Act 2023 regime, but the Council's Contract Standing Orders require construction contracts between £100k and the legislative threshold to be tendered via Constructionline with a minimum of five tenderers invited.

The report also addressed the Public Sector Equality Duty (PSED) under section 149 of the Equality Act 2010, stating the Council's commitment to eliminating discrimination and advancing equality of opportunity. The proposed redesign of the existing kitchen and first-floor staff area was noted to improve functionality and staff experience.


  1. The Just Transition Plan is a strategy by the London Borough of Newham aimed at addressing climate change and ensuring a fair shift to a green economy, focusing on reducing carbon emissions and promoting sustainability. 

Attendees

No attendees have been recorded for this meeting.

Topics

Just Transition Plan Salix Corporate Plan 2022–2026 Roman Road School - Phase 1 Decarbonisation Works Department for Education Public Sector Equality Duty Newham Just Transition Plan 2023 Constructionline

Meeting Documents

Agenda

Agenda frontsheet 28th-Jul-2026 11.21 Officer Key Decision.pdf

Reports Pack

Public reports pack 28th-Jul-2026 11.21 Officer Key Decision.pdf

Additional Documents

Roman Road School Decarbonisation Works - Phase 1 Legal 17.07.26._.pdf