Lincoln Castle Wall Repairs Programme
April 8, 2026 Executive (Other) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Executive of Lincolnshire Council decided on 08 April 2026 to approve the Capital Programme for emergency repairs and Planned and Preventative Maintenance at Lincoln Castle. They also approved the undertaking of a procurement process for the 2026/27 capital works. Authority was delegated to the Executive Director of Place, in consultation with the Executive Councillor for Children’s Services, to progress the procurement process and award contracts.
Full council record
Decision
- That the Capital Programme for the emergency repairs and Planned and Preventative Maintenance (PPM) as set out in the report, be approved.
- That the undertaking of a procurement process for the delivery of the 2026/27 capital works, be approved.
- That authority be delegated to the Executive Director of Place, in consultation with the Executive Councillor for Children’s Services, to take all decisions necessary to progress the procurement process up to and including determination of the final form contracts and the award and execution of all necessary contracts and other documentation required to deliver the capital programme and PPM Schedule.
Related Meeting
Executive - Wednesday, 8 April 2026 - 10.30 am on April 8, 2026
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 8 Apr 2026 |
| Expected date | 8 Apr 2026 |
| Originally due | 8 Apr 2020 |
| Lead officer | Dave Pennington |